How Long Does Siding Installation Take?

Table of Contents

Key takeaways

  1. Most James Hardie siding projects in Kansas City take about seven days on average.
  2. Smaller Cape Cod-style homes can be finished in four to five days.
  3. Larger homes in areas like Overland Park and Mission Hills often run seven to ten days.
  4. Weather and the old material being removed are the two biggest factors in the timeline.
  5. Stucco or cedar shingle removal can add roughly half a day to a full day to the job.

A siding replacement disrupts your home for as long as the crew is on site, so a realistic timeline is one of the most important things to nail down before work starts. The honest answer depends on the size of your house, the weather, and what comes off the walls first. From tear-off to final installation, our Kansas City siding installation projects average about seven days, and below we break down what moves that number up or down.

Our Average Siding Installation Timeline

Most of our projects follow a predictable schedule because the same trained crews handle every job.

A Typical Siding Installation Schedule

Our average install takes about seven days. That window covers removing the old material, prepping the walls, and installing all new James Hardie fiber cement siding.

Across the homes we work on, the low end runs about five days, and larger homes with a full tear-off and replacement can reach ten days. Where your home falls in that range comes down to its size and the handful of factors we cover below, so the seven-day figure is a starting point rather than a fixed promise.

Smaller Homes vs Larger Homes

Size changes the schedule more than anything else. A compact home has far less wall area to cover than a larger one, so the crew moves from tear-off to final board in fewer days.

  • Smaller homes: Many Cape Cods in Fairway, Prairie Village, the Plaza, and Merriam finish in four to five days.
  • Larger homes: Bigger houses in Overland Park, Olathe, Lee’s Summit, and Mission Hills usually take seven to ten days.

We work across all of these Kansas City neighborhoods regularly, so we can give you a realistic day count for your specific home before the job starts.

Key Takeaway: Plan for about a week on an average home, with smaller homes closer to five days and larger ones up to ten.

What Affects How Long the Job Takes?

Two factors move the timeline up or down on nearly every project.

Weather Conditions

The weather is the one factor we cannot control. Rain or extreme cold can pause work and push the finish date back, which is why we build some flexibility into every schedule.

Removing the Old Material

The biggest factor most owners never think about is what comes off the wall first. Stucco and cedar shingles are harder to remove, so they can add about half a day to a full day to the job.

That removal work happens before any new board goes up. The harder the old material is to strip off cleanly, the more it shifts the finish date, which is why we look closely at your existing exterior when we set your timeline.

Pro Tip: If your home has stucco or cedar shingles, plan for one extra day so the timeline still feels comfortable.

Need expert help with your siding installation? Contact Fairway Exteriors for a free consultation.

Why Our Crews Finish on Schedule

Experience is the reason our timelines hold.

Trained Crews and Proven Processes

We follow written procedures and processes, train constantly, and send the same crews and the same crew leads to every job. That consistency keeps each install efficient and on time.

Because the same people install our siding day after day, they know every step before they start. That removes the guesswork and rework that can slow a job down, so your project keeps moving without surprises.

Two Decades of James Hardie Expertise

Before founding Fairway Exteriors, our founder, Scott Neidow, spent nearly twenty years at James Hardie, training thousands of contractors on the most efficient way to install fiber cement siding.

Frequently Asked Questions

  1. How long does an average siding job take?

About seven days for a typical Kansas City home.

  1. What is the fastest a project can be finished?

Smaller Cape Cod-style homes can be done in four to five days.

  1. Why do larger homes take longer?

Bigger homes in areas like Overland Park and Mission Hills have more square footage to cover, which extends the work to seven to ten days.

  1. Does the old material affect the schedule?

Yes. Stucco and cedar shingles take longer to remove and can add half a day to a full day.

  1. Can the weather delay the project?

Yes. The weather is the main factor outside our control and can extend the timeline.

Schedule Your Siding Project in Kansas City

The honest answer is that most homes take about seven days, with smaller homes finishing sooner and larger ones taking up to ten. Our trained crews and proven process keep your project on track from the first board to the last. Contact Fairway Exteriors today for a free estimate and dependable siding installation you can count on.